Sapanca/Esme 800 mm HDPE Pipeline Project
For providing watering Sapanca/Esme region from lake, 120 m length and 800 mm diameters of HDPE pipe line has been mounted on the lake surface. The excavation of the line, underwater services and upper filling services has been taken over by our firm and a floating excavator has been used in the operation.
By bringing down 16 tons of concrete water taking structure on the line and the bounding has been done and the work has been completed.
DENTA SCOPE
- Complete excavation,
- Ground leveling,
- Installing the pipeline,
- Underwater works,
- The connections from the Intake structure,
- Back fillers,
- 2X 12 -12 meters depth installation of concrete water intake structure.