Muğla/Marmaris Sinpas Kizilbuk Underwater Pipeline Project

Underwater 710 mm HDPE pipeline project was carried out for the cooling water supply of the hotel located within the scope of Sinpaş GYO Kızılbük resort project in Marmaris.

Except for the immersion of the pipes, all other works were completed.
Onshore excavation of the water intake structure was carried out.
The work was stopped during the dewatering phase.

DENTA SCOPE

  • 710 mm HDPE boru hatlarının alın kaynaklarının yapılması,Butt welding of 710 mm HDPE pipelines,
  • Pipes being towed out to sea,
  • Manufacture of immersion blocks, their installation in the pipe,
  • Installation of chlorination lines,
  • land excavations,
  • All the diving stuff,
  • Reporting, archive creation,
  • Supply of all equipment,
  • The supply of the whole team,
  • Setting up the dredging barge and making it ready for dredging.

İŞVERENİMİZ : SİNPAŞ GYO AŞ.