Desan Shipyard 6000 m3 dredging Project

Istanbul/Tuzla Shipyards Region, DESAN Shipyard’s current pier and quay fronts were deepened by digging with Sea-I Dredge. Sandy and muddy settlements due to excavation were carried by 900 m3-capacity dropping barge supplied by our employer. Deepening works were also carried out in pile spaces in order that current pier piles into the sea would be removed easily. Dredged m3 amount is approximately 6.000 m3.

DENTA SCOPE

  • Execution of dredging works,
  • Operation of floating excavator,
  • Filling the dropping barge,
  • Completion of the work on time.

İŞVERENİMİZ : DETEK SEA TECH LTD

Related Projects
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.

Not readable? Change text.

Start typing and press Enter to search